P3e - Jumping Activities

S
Steven Oliver 👤 Member for 23 years 8 months

Could try copying your start date to a UDF, then using this field as your sort criteria as it will be unaffected by your update.





HTH


K
Karl Wilkinson 👤 Member for 22 years 7 months

Mario,

Thanks for the reply, I do need to sort the data using WBS and a Start Date (descending) for reason of comparison with hard copy progress reports. It would be useful if I could turn this function off once data has been sorted such that data does not ‘jump’ rows. However once the function is in fact turned off P3e seems to revert the order back to a default (so does not correspond with hard copy reports).

Any further help??