Merging Schedules w/ Different Planning Units

3 replies [Last post]
Kashyap Mothali
User offline. Last seen 13 years 3 weeks ago. Offline
Joined: 4 Apr 2005
Posts: 23
Groups: None
I tried merging two P3 files - each with a different planning unit i.e., one has "Weeks" and the other has "Days".

I first copied the file with "Weeks" and changed it’s unit to "Days". I used this copied version as the host and brought in the file with "Days".

P3 did not convert the host file’s "Weeks" to "Days". The numeric value of the OD remained unchanged but with different units. This doesn’t serve me any purpose.
e.g., 1 week became 1 day and NOT 5 work days.

Is there a way to have P3 convert the OD automatically from weeks to days (assuming the default Cal #1)?

Thanks,

Kashyap

Replies

Kashyap Mothali
User offline. Last seen 13 years 3 weeks ago. Offline
Joined: 4 Apr 2005
Posts: 23
Groups: None
I guess a Global Change would solve the trick but it wouldn’t apply to ’lags’.

Thanks for the suggestion,

Kashyap
David Kelly
User offline. Last seen 2 years 16 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
There are two reasons why you would merge projects with different planning units.

1) Summary reporting, i.e. the output project does NOT need to be scheduled. In this case the dates that come across for the "mixed" planning unis are correct and the summary project should NOT be scheduled.

2) Further scheduling. A global change will be required to change the durations of either the "daily" or "hourly" activities. This MUST be run before you schedule.
Sukumaran Subaram...
User offline. Last seen 9 years 18 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Use Global Change to make the changes.

Regards.