Showing the Progress in Bar Chart View

4 replies [Last post]
Evren Tufekciler
User offline. Last seen 15 years 18 weeks ago. Offline
Joined: 11 Jun 2005
Posts: 7
Groups: None
I create the target plan and update. In bar chart view, I want to see the planned bar and the progrees bar at the same time. How can I do it?

Replies

prem kumar,
User offline. Last seen 13 years 13 weeks ago. Offline
Joined: 9 Mar 2005
Posts: 14
Groups: GPC Qatar
u can e mail to me, the file at prem_k_s@yahoo.com
Razi Khan
User offline. Last seen 8 years 4 weeks ago. Offline
Joined: 17 Jun 2004
Posts: 74
Groups: None
Hi,

Increase the row’s height.
Evren Tufekciler
User offline. Last seen 15 years 18 weeks ago. Offline
Joined: 11 Jun 2005
Posts: 7
Groups: None
Thank you for reply.

I tried but it didn’ t work. Nothing changed only I can see the summary bar. Also I click the visible button. Can I send the file Which you can do it?

Sincerelly yours.
Hemanth Kumar
User offline. Last seen 1 year 16 weeks ago. Offline
Joined: 1 Nov 2002
Posts: 260
Groups: None
Dear

Format-bars, +, name it ,position 2, start-=target-1 early start, finish +target1 early finish

thats it