Show P3 trace logic in bar chart

2 replies [Last post]
Anu Tor
User offline. Last seen 13 years 37 weeks ago. Offline
Joined: 7 Mar 2007
Posts: 53
Good afternoon,

I want to trace the driving logic of predecessor and successor in bar chart same as pert chart.

Anyone can recommend me the method to do in P3 or other software to support one.

Thanks,

Replies

Anu Tor
User offline. Last seen 13 years 37 weeks ago. Offline
Joined: 7 Mar 2007
Posts: 53
Hello Ali Farhat,

In normally, P3 will show all links if select one. In sometime, If I select a activity and want to see 3 level of predecessors and successors of one in bar chart format.

Please recommend me.
Ali Farhat
User offline. Last seen 14 years 11 weeks ago. Offline
Joined: 23 Oct 2008
Posts: 120
Groups: None
Anu,
I didnt get your question perfectly...anyhow, driving relationships are displayed in Gantt and pert chart as solid lines while nondriving relationships are displayed dotted line.
Is that what you want?