Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Suspended of work

12 replies [Last post]
Wassem Habboub
User offline. Last seen 12 years 49 weeks ago. Offline
Joined: 13 Aug 2005
Posts: 7
Groups: None
Dear all

How I can illustrate suspended of work for all task in P3?

If I have two period of suspended for the same task
Can P3 illustrate this case?

Thanks
W.H

Replies

Hannes de Bruyne
User offline. Last seen 2 years 8 weeks ago. Offline
Joined: 25 Jul 2005
Posts: 154
Groups: None
Hi Clive,

even if the suspended work is your own fault, keep track of it in your timeschedule. If later you see that there is a concurrend delay it may get very important to see which part is yours and which part is due to the client. If you hide your problems, client has most opportunities to give all the problems to you if there is a concurrend delay.
So my opinion is to show own delays as well as they are know to verebody anyhow.

Hannes
Clive Randall
User offline. Last seen 16 years 46 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
Sen
Good point but I trust the work is only being suspended by way of a formal instruction from the client or his rep. If the suspension is due to other reasons ie contractors fault i would suggest forget showing it on the programme and get planning a recovery.
Sen Moc
User offline. Last seen 18 years 44 weeks ago. Offline
Joined: 30 Aug 2005
Posts: 123
Steven,

In this case, in addition to creating a calendar for the suspended work periods, might as well fill-in the Log Form with a note for the reason of suspension (reference memo, minutes of meeting, instruction from the Project Managers/Cleints, etc.)

Sen
Steven Oliver
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Agreed, there are many ways suspension can be displayed, but please remember 2 or 3 years from now, when people have moved on to other things, or been run over by a bus (not a threat) that someone may have to re-trace the history of a project (in support of a claim, for example) having a plan with a curtain, or a defined resource calender wouldnt really help.


Hannes de Bruyne
User offline. Last seen 2 years 8 weeks ago. Offline
Joined: 25 Jul 2005
Posts: 154
Groups: None
of course there is a dirty trick - if you also show a resource-bar and the beginning of the resource is behind the activity end, then you see two bars in one line - but if you suspend work, there is an important reason for that. This reason should not be forgotten somewhere in the future, so make an activity out of it.

Hannes
Clive Randall
User offline. Last seen 16 years 46 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
Of course another option is not to use P3 at all but powerproject which would enable you to put the suspension bar in all activities but if P3 is to be then the calendar option gives you the best representation. If you want you can then save as an ADOBE file take into powerpoint and add whatever graphics you want.
Up to you
Clive
Zhang Haixiang
User offline. Last seen 4 years 4 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
Alex,

if someone says 1+1=2, then I can’t say that any more?

for the author of this post, he’ll see at least 2 PPers suggest to do this way.

Back to the question,(sorry for repeating your...)

another option print the schedule to a bitmap file, then open with picture processing software (e.g. photoshop), then draw whatever you want.
Alex Wong
User offline. Last seen 11 years 32 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
zhang

I been following some of your posting. Please consider not to repeat other members message.

Back to the question,

Another option you can show in the schedule when you want to show a suspended period of works. Using the Curtin provided in P3 where when you printing the schedule it is shaded and you can put some comments against it. It will clearly show that period is not working.
The command is in ’VIEW’ - ’ Attachment Tools’

Of course you still need to adjust either your calenda or supspend the activities.
Regards
Alex
Zhang Haixiang
User offline. Last seen 4 years 4 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
I agree with Ronald.
Ronald Winter
User offline. Last seen 3 years 34 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
I would recommend that you copy your calendar and make a new one called "Suspension." Put in the suspension period(s) as holidays. Then assign those suspended activities to this calendar. Show holidays as necking on your display. Good luck!
Steven Oliver
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Much better to create new activities defining the duration of suspension (and the reasons).

Marcio Sampaio
User offline. Last seen 12 years 9 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Dear all,

Think u have an option to show "Necking Bars" on bars options (click with right botton on grant chart).

Regards.

Marcio Sampaio