Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P3 to P3e convert.

2 replies [Last post]
Marcio Sampaio
User offline. Last seen 12 years 13 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Dear all,

I’m working with planning and control in a oil company in Brazil.
My company works with P3e and my contractor works with P3.
Do u know if i’m going to have problems - like loose infomrations - during update using P3e to P3 convert and P3 to P3e convert?

Regards.

Marcio Eduardo

Replies

Alex Wong
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
I suggest you have to test run it first for P3e-P3-P3e

I cannot see a great problem if your import and export setup is correct. Meaning the updating code, resource code, activity code, calenda, WBS.

P3e - P3 should be simple All information should be there
P3 - P3e require a bit of co-ordination between you and your sub becasue P3 only have limited activity and project code (and limited lenght as well) you have to do some global change to convert it to your master schedule
Regards
Alex
Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Basically, dont go there.

P3e has so many things which P3 doesnt.

You will spend massive amounts of time checking the results.