Microsoft Project : Resources and Resouce Groups

4 replies [Last post]
Jim Parker
User offline. Last seen 19 years 10 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 7
Groups: None
Guys,

Need a hand! I have resources by name and I also need to collect them by function e.g. "Jim" in "commercial". How do I do it?

Replies

Jim Parker
User offline. Last seen 19 years 10 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 7
Groups: None
Thanks!!
Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Ok,

Have you tried using one of the text fields to contain your dept, apply a filter based on this field and then view by resource.


Jim Parker
User offline. Last seen 19 years 10 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 7
Groups: None
I tried, this but I am unable to allocate just some tasks and not all. How do you make it work?
Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Use the Resource Group field