Scope changes and P3

2 replies [Last post]
Vanessa Morris
User offline. Last seen 19 years 5 weeks ago. Offline
Joined: 4 Jul 2005
Posts: 13
Hello, when a project is underway you have your target a current schedule. How do you deal with scope changes, additional/extra works with your schedule in P3. Do you add this new activities into your current schedule? Thanks.

Replies

Charleston-Joseph...
User offline. Last seen 3 years 14 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hello Vanessa,

Yes, you have to include the changes in scope of work, variation order, etc., in your schedule.

Generally, if you are using Work Breakdown Structure, you will add a new WBS- 50.000 Variation Order, Changes, etc. You can further make a new sub-level: 50.100 Provisional Variation Order, 50.200 Extension of Time (in case you will be going into extension of time, etc.

The above is an example only. I hope it help you.

Cheers,

charlie

Raja Izat Raja Ib...
User offline. Last seen 13 years 23 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
hi vanessa
if we looked at the contract, if the activities is out from the scope we add under title VO or addtional scope but if it is activities lefted behind u can see at below post how u going to add activities.