Retained Logic Question

S
Sunil Kumar 👤 Member for 21 years 2 months
B
Bernard Ertl 👤 Member for 23 years 7 months

Sunil, perhaps it may be a calendar phase problem. Check the calendars for any FF predecessors (I suppose ancestors is a better word - you may have to check several tasks preceding) to see if they are delaying the task (even though the predecessor is completed).



I remember seeing this problem on some scheduling system back when I was doing some testing, but I honestly don’t recall which system exhibited this behavior.



Bernard Ertl

eTaskMaker Project Planning Software

E
Ernesto Puyana 👤 Member for 25 years 5 months

It could be that your program is linking percent complete to remaining duration.

F
Frank Borcherdt 👤 Member for 25 years 1 month

Check constraints, suspend and resume dates and calendar of 90% complete activity.



If using Projects within Project Groups check advanced scheduling options re Data dates.



There has to be a logical reason and I consider progress overide fairly dangerous for the reason I explained before.

Forum Sponsor

Top Posters

GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts