Retain logic

3 replies [Last post]
Ranish KT
User offline. Last seen 45 weeks 4 days ago. Offline
Joined: 30 Jan 2003
Posts: 28

Hi Planners

Total float for activities dont reflect correct picture while we use progress override option in scheduling. Why is this so, can anyone pls explain.

Regards
Ranish

Replies

Jorge Taguinod
User offline. Last seen 2 years 44 weeks ago. Offline
Joined: 8 Jul 2003
Posts: 139
Total float computation will be different for progress override and retained logic. Both will be correct, depending on your perspective.

The problem here is that you can only set one option to apply to ALL activities. It would have been nicer to apply different options to different activities.

So, with the current state of things, you need to decide which one to use. Retained logic gives you a more conservative projection of how things are going to be. So if you want to be on the safer side, user retained logic.

Jorge
Crown Systems (Philippines)
Forum Guest
User offline. Last seen 12 weeks 4 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Hi guest member,
Thankyou very much for the site, I have registered and made a comment on the topic.
Ranish
Forum Guest
User offline. Last seen 12 weeks 4 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Ranesh, This might help you as a reference, pls. visit this web address- http://www.pmicos.org/cgi-bin/ubb/ultimatebb.cgi?ubb=get_topic;f=4;t=000003