Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Cost Hammocking

1 reply [Last post]
Rajeev Kumar
User offline. Last seen 9 years 37 weeks ago. Offline
Joined: 27 Apr 2003
Posts: 43
Groups: None
I have got resources & costs on hammocks. Is it possible that I can hammock the hammocks and get a total cost out of it. My intention is to retain the loading of individual activities or hammocks. Is there any other way other than summarizing?

Replies

Steven Oliver
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Could try activities of type "WBS".