Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Level of Effort (LOE) - Activity Type

5 replies [Last post]
Suhaila Tsu
User offline. Last seen 49 weeks 2 days ago. Offline
Joined: 6 Jun 2011
Posts: 25

Dear Experts

For activity type - Level of Effort - why i can't assign duration to it. Every time i hit F9, the duration will go back to Zero.

By the way, i have not assign any baseline. I was just developing my work programme. 

I have tried using the Sucessor FF , but if i use that , the duration would be too long.

FYI, i was assigning  Activity name: Performance Bond as LOE. 

 

Replies

Rodel Marasigan
User offline. Last seen 1 day 19 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

yw happy to help

Suhaila Tsu
User offline. Last seen 49 weeks 2 days ago. Offline
Joined: 6 Jun 2011
Posts: 25

 

Ok. Thank u Rodel Marasigan

Suhaila Tsu
User offline. Last seen 49 weeks 2 days ago. Offline
Joined: 6 Jun 2011
Posts: 25

Alright. Thank u Zoltan Paffy

Zoltan Palffy
User offline. Last seen 3 weeks 6 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you are missing the whole point of a LOE

a LOE has a predcesso with a SS and a successor with a a ff and it AUTOMATICALLY calulates the duration betweeen the predcessor start date and the successors finish date. 

If you you do not want his then change the activity type.

Rodel Marasigan
User offline. Last seen 1 day 19 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Hi Suhaila,

Level of Effort (LOE) or Hammock activity is driven by activity relationship. The start of activity should be link to Activity where it needs to start using (SS) Start to Start predecessor and finish is link to Activity where it needs to finish using (FF) Finish to Finish Successor. See sample below:LOE-Sample

LOE activity does not have duration on its own.