Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Level of effort activity

No replies
Mangesh Khuspe
User offline. Last seen 1 year 6 weeks ago. Offline
Joined: 10 Apr 2007
Posts: 162

Dear All,

 

We have a master schedule prepared for the client and internal use some 2 years back, which was not detailed much at that time, but now as the project is in full speed now we want to monitor it more deeply and want to detail the master schedule more  ( add more detailed activities in same program) and hence delibrating about various options,

1) Can we use the Level of effort activities?.

2) Activity steps would be another option to use.

3) Detail it more in another schedule and calculate the percentages from there and put them back in the master schedule.

4) any other option as suggested by you guys.

Thanks and regards,

Mangesh