Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Problem on Updating

2 replies [Last post]
Stanley Okolorie
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 26 Jun 2019
Posts: 2
Groups: None
Good morningPlease am having issues when reporting, when ever i have to update the percentage work progress in it changes the finished date assigned to it by reducing the actual date and if i try to bring it back to the actual date that is assigned to it, it will reduce the percentage to zero percent. what is cause am confused in P6  Thanks

Replies

Zoltan Palffy
User offline. Last seen 21 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

to update an activity 1st click the started box 

2nd put in the actual date that it started

3rd put in the remaining duration

Santosh Bhat
User offline. Last seen 13 weeks 3 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

When in Activity View, select the Activity Details at the bottom of the screen, in the General Tab, check that the % Complete Type is set to Physical not Duration.

You may need to check for all activities - you can do this by adding the % Complete Type  column to the activity view, changing one, select the ones you wish to change and then right-click and select "Fill Down"