Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

S-Curve analysis

6 replies [Last post]
djedilat toumi
User offline. Last seen 4 years 23 weeks ago. Offline
Joined: 14 May 2018
Posts: 9

Hello everybody, 

Please, can you comment on this S-curve and give us some explanation about it?

waiting your comments....

regards

5737
construction S-curve .png

Replies

Rafael Davila
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

1) As per image legend, blue and green lines represent planned schedule, perhaps from a baseline schedule with no progress.  Actual [red solid line] and to complete early [black slash line] represent current schedule, missing to complete late that should start at same point to complete early starts.

The image shows different versions of the schedule, each with different data date.  For those with no progress, no actuals, their data date happens at first point. For those with progress data date happens where actuals finish and remaining [early&late] starts.

2) Any update of progressed schedule shall match actual to the left of data date, to the right it will show updated early and late lines.

djedilat toumi
User offline. Last seen 4 years 23 weeks ago. Offline
Joined: 14 May 2018
Posts: 9

thank you a lot Mr. Rafael Davila

i didn't get well some points:

1- At Data Date the remaining [to complete] early curve and remaining [to complete] late curves must start at same point.

in my S-curve they didn't start at the same point (see the black circle), is there a problem in my curves??

2- is it normal to find a curve of the revised plan like this ( see the black line)

5853
sans_titre.png
 

5854
sans_titre.png

Mick C
User offline. Last seen 1 year 1 week ago. Offline
Joined: 15 Jul 2018
Posts: 6
Groups: None

Hey is anybody producing these S-Curves unsing costs with Asta PP? I am pretty new to this side of things. I am putting together a forecast of a cost loaded and resourced programme to track 2 internal budgets, and then plan to update actuals throughout the project to keep track of any variations which may occur. 

Am I right in saying that  to include 2 internal budgets, one on BOQ estimates, and another on Tender actuals, Would I be right in saying that to produce both curves I need to baseline the project 2 times in its original "planned schedule position"? and then rejig the amounts for the second baseline?. Essentially what I plan to do is:

  1. Load in costs which have been broken down to the activity level from a BOQ, then baseline.
  2. Delete the above costs, and load in Tender/Actuals, then Re-basleine the project in the same position.
  3. Record Actual cost (Variations) throughout the project in line with Progress. 

Does this approach sound like the right way to go about this?

Rafael Davila
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
SCurve123
  • By looking at the Actual Curve end point we know the Data Date. 
  • The remaining late curve for current schedule is missing, shall be something like the one I draw in solid black. 
  • At Data Date the remaining [to complete] early curve and remaining [to complete] late curves must start at same point. 
  • Any revission to current schedule shall include remaining early and late starting at the same point, the last actual point.
  • Usually early curve is above late curve but the use of FNLT constraints can make them intercept at some point and then late curve to be above.  It does not always happens but the S-curves even when not obvious can become meaningless when such constraints are used.  Not all schedulers are aware of this anomaly.
  • There is a reference to interpreting S-curves, the AACE International Recommended Practice No. 55R-09.  I do not recommend it as it misses to talk about the anomaly when using FNLT constraints and even misses to talk about early and late S curves.  Anyway I feel you should be warned about it. 
djedilat toumi
User offline. Last seen 4 years 23 weeks ago. Offline
Joined: 14 May 2018
Posts: 9

thank you a lot Mr. Zoltan Palffy.

is it normal to find a curve of the revised plan like this ????

Zoltan Palffy
User offline. Last seen 4 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

this is either a manhour or cost based resource driven s curve

the Y axis respresnts the % complete and the X axis respresents a time inter vale (too samll to read) in eather weeks or months

The blue line represents the earliestdates that actviities can be started and completed

The green line represents the latest dates that actviities can be started and completed

The red line represents progress or actuals against the plan

Te red dashed line represents the revised plan 

The dashed lines is the forecasted percentages to meet the revised plan