Updating Existing Project for new Baseline

4 replies [Last post]
Anderson Charlie
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 25 Apr 2016
Posts: 13

Hi,

Recently I have just amended my resources cost. I want to update my cost baseline by updating the current project by importing previous updated *.xer files. However, when I try to schedule my program it become 0% (except for the 100% activities). Can anyone advise me why does this happen? Or do I have to manually insert in the performance percentage manually one by one to each of the activities. Which by the way consist of more than 500 activities!!!

Thanks in advance guys

Replies

Zoltan Palffy
User offline. Last seen 21 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad I could help 

Anderson Charlie
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 25 Apr 2016
Posts: 13

Hi Mr Zolfan,

Your method works!! thanks for the reply.

Anderson

Amro Ahmed
User offline. Last seen 2 years 39 weeks ago. Offline
Joined: 5 Jan 2009
Posts: 107

Please also Make sure the following:

- No filter has done in the update  especially,(in progress activities)

-in update , the option for thechnique  computing pecent comletion is custom  not 0/100

 

Good luck

Zoltan Palffy
User offline. Last seen 21 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

assign the baseline then select update baseline and select costs