Dear All,
What would it be the best, efficient way to manage an EP C CM (where C is construction and CM is pre&commissioning) schedule with 4 main construction sub-contractors and important client interfaces (utilities supply and permits).
The EP C CM schedule has been split in 3 linked schedules:
- EP schedule (engineering + procurement): linked to construction.
- C schedule (Construction) : linked to pre and commissioning.
- CM schedule: includes pre and commissioning.
The C schedule contains 4 construction contractor schedules:
For the main subcontractor (2), their schedules have been included in the master C schedule (construction)
- Doing this for the first time is not a problem. The problems starts with the weekly update. Very difficult to keep up the master fully aligned with changes done by subcontractor. The master schedule will start reporting inconsistencies and inaccurate information about activities.
I do not like this practice, I would rather define KEY milestones in subcontractor schedule and place the milestones in the master schedule.
Is there any different way about this practice??
Client interfaces: I would rather add milestones in the master EP C CM schedule.
Avoid adding activities. Reason for this is the update.
Is there any different way about this practice?
Thanks in advance for your input,
Regards,
Carmen
Replies