Scope Change- additional project to existing project

Member for

19 years 10 months

Hi Sharaf

Since the two new buildings are being treated as a variation to the original 6 building contract then all 8 buildings should be put into the same baseline programme and a new completion date negotiated.

Never have two contracts on one site with one contractor - massive problems will flow from that scenario.

Best regards

Mike Testro