Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Report: Current Week Activities

4 replies [Last post]
Stefano Squadrani
User offline. Last seen 8 years 24 weeks ago. Offline
Joined: 13 Jun 2016
Posts: 3
Groups: None

Hello Guys,

I would like to create a report that displays the to-do list of the acitvities grouped by project of the current week, supposed that I run the report on monday. I cannot manage to create it. How can I make it?

 

Thank you

Replies

Raymund de Laza
User offline. Last seen 3 days 21 hours ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hi,

Suggests to assign activity codes to use for grouping and filter using Current Day+7d

 

Robert Bell
User offline. Last seen 6 years 21 weeks ago. Offline
Joined: 8 Jun 2016
Posts: 49
Groups: None

Hi Stefano,

You can do this by filtering for the dates. The only thing to be wary of is if you filter for work in the fourth week of the month for example, but the activities for the first three did not go as planned and are still open.

Robert Bell
User offline. Last seen 6 years 21 weeks ago. Offline
Joined: 8 Jun 2016
Posts: 49
Groups: None

Hi Stefano,

You can do this by filtering for the dates. The only thing to be wary of is if you filter for work in the fourth week of the month for example, but the activities for the first three did not go as planned and are still open.

Stefano, it depends on the software that you use.

In Spider Project you just select the period and that's all. It is standard function.