Report: Current Week Activities

4 replies [Last post]
Stefano Squadrani
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 13 Jun 2016
Posts: 3
Groups: None

Hello Guys,

I would like to create a report that displays the to-do list of the acitvities grouped by project of the current week, supposed that I run the report on monday. I cannot manage to create it. How can I make it?

 

Thank you

Replies

Raymund de Laza
User offline. Last seen 9 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi,

Suggests to assign activity codes to use for grouping and filter using Current Day+7d

 

Robert Bell
User offline. Last seen 6 years 7 weeks ago. Offline
Joined: 8 Jun 2016
Posts: 49
Groups: None

Hi Stefano,

You can do this by filtering for the dates. The only thing to be wary of is if you filter for work in the fourth week of the month for example, but the activities for the first three did not go as planned and are still open.

Robert Bell
User offline. Last seen 6 years 7 weeks ago. Offline
Joined: 8 Jun 2016
Posts: 49
Groups: None

Hi Stefano,

You can do this by filtering for the dates. The only thing to be wary of is if you filter for work in the fourth week of the month for example, but the activities for the first three did not go as planned and are still open.

Stefano, it depends on the software that you use.

In Spider Project you just select the period and that's all. It is standard function.