Dear All,
I'd like to know what the best practice and/or your experience is with:
1) Obtaining planned resource from and an update schedule (budgeted? / baseline? / remaining?) to compare against actual from timesheets/daily reports.
2) Forecasting required resources for the next update period (budgeted? / baseline? / remaining?)
3) Deciding on how much resource to add (if any)
Knowing that the updated schedule has slippage.
Note that I’m trying to avoid the simple planned resource histogram established at the time the Baseline was established; which is obviously updated every reporting/update cycle with actual resource for comparison. I see the dynamics of an updated schedule might render such a curve rather useful due to factors like out of sequence work and such!
Please also note that by resource I’m generally referring to manpower/plant and not material.
I hope the question is clear!
I appreciate your expert input.
Replies