I have prepared a Baseline in P6 but it is not approved due to several comments. The Main comment which is making problem for me is float. My activities has float over 200 and client instructed do not exceed total float than 80.
All milestone activities are not critical & as per requirement should be critical. I have also changed my Critical Path method to the longest path.
I have tried to change the relationships but it is not changed as I did not run the schedule but if I will press F9 and will run the schedule all the duration/ dates will be changed as relationship of the each activity is not yet final. So how can I know that whatever changes I am doing with relationships will be effective for me or not!
Even I donot exactly know what will is a logic to reduce the float.
Please help me out to solve the issue.
Thanks & Best Regards.
Replies