Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

WBS

4 replies [Last post]
Mike Melay
User offline. Last seen 5 years 29 weeks ago. Offline
Joined: 12 Jun 2012
Posts: 13
Groups: None

Hi All,

Just having a discussion on a recent schedule for a program I am working on, where an activity did not occur and has now been highlighted as a miss from the WBS. It is involved cycle development of piece of equipment.

The standard WBS we use calls out cycle development and is further broken down in(1) protcols / documentation, (2)execution and (3) reports. I break out each of these per piece of equipment as needed and picked up during the interactive planning session.

Can anyone telll me what is the level a WBS needs to go to, ie. what exactly should be captured in a WBS. My understanding is it should be high level and each task cpatured at activity level. Your WBS should not cover Level 3 or Level 4 activities?

Would be grateful to get feedback here

Thanks,

Mike

Replies

Raymund de Laza
User offline. Last seen 12 weeks 4 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

WBS is simply similar to a Folders.

2093
folder.jpg

Dennis Hanks
User offline. Last seen 8 years 45 weeks ago. Offline
Joined: 17 Apr 2007
Posts: 310

Mike: For me it is at whatever level you can/should collect costs (data).  It is conceivable, though not practical/realistic, to take a WBS down to the individual craftsman/crew.  In reality, it is the ability of the estimator to estimate to a proscribed level of detail that will determine the granularity of the WBS.  The estimator will collect his quantities in accordance with the existing WBS.  In my world, my little portion of it, the WBS is usually geographic - project, phase, building/structure, craft/discipline, level, quadrant, etc.  The cost accounts should reflect this.  The CBS should map to the WBS.

There is no reason to collect (code) data below the level of the current estimate.  This level will change with project maturity.  The level of the WBS depends on where you are in the project chain/process.

Mike Melay
User offline. Last seen 5 years 29 weeks ago. Offline
Joined: 12 Jun 2012
Posts: 13
Groups: None

Thanks for the feedback Patrick - much appreciated

Mike

Patrick Weaver
User offline. Last seen 6 hours 10 min ago. Offline
Joined: 18 Jan 2001
Posts: 384
Groups: None

Agree Mike!  The WBS Work Packages are the lowest management level defining a deliverable of some type.  Each Work Package devolves into many schedule activities that define how the work needed to create the deliverable will be accomplished. For more on this see:  http://www.mosaicprojects.com.au/WhitePapers/WP1011_WBS.pdf

The ‘size’ of the work package is less important than it representing a self contained block of work that is assigned to a manager to manage, ether stand alone or as part of a control account.