Global WBS or Project Specific WBS

1 reply [Last post]
Richard Day
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 10 Jul 2008
Posts: 11
Groups: None
In Primavera 6.1 is it better to use a Global WBS or a Project Specific WBS?

I am scheduling about 100 projects with monthly updates.

Replies

Dieter Wambach
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Depends on your needs for reporting.
Internal projects, stakeholders need reports on all projects: Global wbs to e.g. level 2 or 3, more in detail, upon pm’s decision.
Independent projects with different stakeholders: Easier for you with a standard wbs (templates!). May depend on the projects’ stakeholders.