Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Graph

6 replies [Last post]
Ammar Tauqeer
User offline. Last seen 10 years 47 weeks ago. Offline
Joined: 6 Oct 2013
Posts: 22

Dear All,

I want to have a graph between how much Perfomance% has been completed with respect to schedule %(of the whole Project).

Replies

Ammar Tauqeer
User offline. Last seen 10 years 47 weeks ago. Offline
Joined: 6 Oct 2013
Posts: 22

I can only enter schedule % complete data upto current data date.But i want to have schedule % complete of the whole project before hand.

Ammar Tauqeer
User offline. Last seen 10 years 47 weeks ago. Offline
Joined: 6 Oct 2013
Posts: 22

Thanks Mike.I want to show schedule % Complete(the problem is that i dont know how it is giving weightages to the activity and then to whole WBS) with Performance % complete Graph.(This is generated by the work i have done)

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ammar

This kind of data is best generated on an Excell Graph.

Copy the percent complete numbers into an excell sheet from both the actual and target and use the data to present a vertical bar graph for each section of work.

Keep the graph format for the next progress update.

Best regards

Mike Testro

Ammar Tauqeer
User offline. Last seen 10 years 47 weeks ago. Offline
Joined: 6 Oct 2013
Posts: 22

Told them to do so but they want progress in terms of duration.

How much performance % is completed of Planned %

Raymund de Laza
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Show the Planned Value Cost and Earned Value Cost Curves.

Ammar Tauqeer
User offline. Last seen 10 years 47 weeks ago. Offline
Joined: 6 Oct 2013
Posts: 22

Or you can say i want to track my project graphicaly