Vico Control2009SP3 resource graph behavior

1 reply [Last post]
Forest Peterson
User offline. Last seen 8 years 31 weeks ago. Offline
Joined: 22 Mar 2011
Posts: 33

Does the resource graph represent the baseline plan and the actual+forecast?

Replies

Forest Peterson
User offline. Last seen 8 years 31 weeks ago. Offline
Joined: 22 Mar 2011
Posts: 33

I made a simple test:move Laborer resources from week1 to week 2; current 18 laborers
      * in control mode
      * move 5 days SWEEP fiberroll
      * move 3 days sweep silt
      * change to design mode
      * refresh and reforecast
      * change back to control mode

The result: still 18 laborers but it looks like something changed

Conclusion: I will test more