Hi there,
For no reason I can tell, my schedule has suddenly started showing Group Totals in my layout that do not add up correctly, although the activity durations are correct.
From past experience this is usually a calendar issue. I am using a Project Calendar, and the Hours per Time Period checkbox to use assigned calendar is ticked. I am using a 11hr / Day, 7 day a week calendar. Upon looking into the Global calendars, a 38hr week calendar is clicked as a default. Could this be causing the issue? I have done some calculations and it appears that some of the totals are being calculated on a 38hr week, but not in every case.
I know the Global calendar issue was a problem in V6.0 but I was under the impression that the Project Calendar would overide in v7.0. is this the case?
Is there something else I may be missing? The only major work that has been done recently is a colleague removed all the WBS Summary activities from the schedule.
Can anyone provide any way forward?
With Regards,
Replies