Remaining Units are not calculated correctly in Primavera P6

1 reply [Last post]
Mahmoud Azab
User offline. Last seen 9 years 13 weeks ago. Offline
Joined: 29 Mar 2015
Posts: 2
Groups: None

When updating a Baseline project and giving an actual start to a task dependant activity , the sum of remaining units and actual units is not equal to the budgeted units.

Any ideas why this happens?

Replies

ssp ssp
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 1 Apr 2011
Posts: 3
Groups: None

check the duration type of activity. is it fixed units?

After updating the progress, if there is any differnce in at complete and original duration, and duration type is fixed units/time, the sum of remaining units and actual units will not be equal to budgeted units.