Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Different types of programs during project life cycle.

1 reply [Last post]
Rami Refaat
User offline. Last seen 6 years 8 weeks ago. Offline
Joined: 17 Aug 2011
Posts: 13
Groups: None

Dear All

I create this topic for the sake of understanding different types of programs during project life cycle, i will mention the types i already know but if someone here can explain all of them one by one and when we can use each of them it would be great for all of us.

What i know is: Baseline, Revised Program, Accelerated Program, Recovery Program & Execution Program.

Note: If this topic is already exist in the forum please refer to the topic in a reply.

Replies

Mike Testro
User offline. Last seen 32 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Rami

Baseline - the original programme.

Revised programme - any changes to the baseline programme which may then become a new baseline

Accelerated Programme - changes to the baseline programme attempting to achieve an earlier completion date.

Recovery Programme - revision to the baseline programme attempting to regain lost time - may include an acceleration exercise.

Execution Programme - not a term I recognise - probably another term for baseline or even a short term look ahead extract.

Hope that helps

Mike Testro