METHOD OF RESOURCING THE SCHEDULE IN P6

Member for

21 years

Hi,

Much like Raymund.

1. Make sure you set interval calculation first to Month for your case. Perhaps this will take care already.

2. In the top pane, open the P6 table that shows resources distrbution per activity.

3. In the bottom pane, shows the graph options that shows resource histogram.

4. With these two pane, go to the activity (top pane) and see the month (bottom pane) with most resource and try to adjust the date or duration in order to level. Repeat.

Member for

15 years 11 months

Dura,

In User preferences.. Resource analysis.. set the interval to the desired time interval.

Also, in the Spreadsheet or graph options in the resource distribution pane, click the calculate average and the the based on hrs per time period.

Hope this will help.