Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

unit/time

3 replies [Last post]
Sunil Babu
User offline. Last seen 5 years 15 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi friends,

I want to change resource unit/time into decimal. In my system default value 1 is coming

how can I change to 0.3 etc..

Regads,

Sunil.

Replies

Sunil Babu
User offline. Last seen 5 years 15 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Arend,

Your answer was not enough for my question. Can you please explain the steps, in the resource  view

how can I change the default uni/time value..?Adding budgeted qty is defferent matter.

Regards

Sunil.

Arend Woltjer
User offline. Last seen 9 years 1 week ago. Offline
Joined: 26 Sep 2011
Posts: 74
Groups: None

Hi Sunil,

you can change the  Default units per time   in the resource view of P6, you have to enter a komma ( , )

When you add a resource to an activity you can change the Budgetted Units. The Budgetted units per time change automaticly then.

 

I hope this answers your question.

 

Regards,

Arend

Gary Whitehead
User offline. Last seen 5 years 24 weeks ago. Offline

what software?