Project Resource Window

3 replies [Last post]
AB Timo
User offline. Last seen 9 years 23 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

Hi All

 

I am Currently Using Primavera P6. I want to see the resources for a specific project project only but Primavera changes Filter From "Current Project" To "All Project Resources" Automatically.Is there any way to see and add the Current Project Resources only????

 

Regards

Replies

Shah. HB
User offline. Last seen 36 weeks 2 days ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi AB Timo 

 

If you want to define new resource ,first thing is to create a resource (For Eg.- abc ) in resource dictionary then move to the respective activity , choose resource tab option  from activity details ,click add resource option and select the filter ""All Resource"" where you can find the newly created resource (abc) then assign to it

 

Cheer's 

Shahul

AB Timo
User offline. Last seen 9 years 23 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

Hi Shahul

Thanks for you Help.But still i can't find the solution.In P6 there are three options

1- Filter by "All Active Resources"

2- Filter By "All Resources"

3-Filter By "Current Project Resources"

 

The Issue I am facing is that i want not to see other Resources in My New Project.I want to define new resources but when I Select "Current Project Resource" and then Press "Add" Button the Filter Automatically Changes to "all REsources"...I have also Tried for "All Active Resources But its not working Either..Can you please explain what yoi have just said.I think i am Not getting it

 

Regards

Shah. HB
User offline. Last seen 36 weeks 2 days ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi AB Timo

When you open resource pool window layout in that, resource icon marked with arrow mark symbol shows currently active resource available for the opened project

 

Regards

Shahul