Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Critical Path Change

3 replies [Last post]
AB Timo
User offline. Last seen 9 years 37 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

Hello All,

I have just come accross an issue that i never faced before.I have Planned a project and after finalizing the baseline when I updated it on the current data date,The critical path has transfered to Non.Critical.Now there is no critical activity in my Whole project.Anyone know the reason behind this??

Replies

Gary Whitehead
User offline. Last seen 5 years 26 weeks ago. Offline

Next most obvious thing to check is if there is a constraint at the project level.

Assuming you are using P6 (most do), you can check this from Enterprise > Projects. Right-click on your project from the EPS structure and select "Project Details". Go to the "Dates" tab and check that the "Must Finish By" field is blank

 

If it's not this, calendars would be the next thing I'd look at.

AB Timo
User offline. Last seen 9 years 37 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

Thanks Mike for The Reply.There is no constraint in my Schedule.I have checked all activities.

Mike Testro
User offline. Last seen 3 days 19 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Faiz

There could be any number of reasons but the most common is that you have some Must End By constraints.

Remove ALL constraints and reschedule.

Best regards

MikeTestro