Dear All,
I am new to PP blogs and require help from your expertise.
I have to report to my Managment some sort of Delay Analysis & Lesson Learned by comparing Baseline and As-built Schedule. I had joined the project in mid of its life, so I have collected reasons of delay from documents and from coleagues before me and recorded separately.
The big hurdle in my way is that the baseline schedule is so brief and different from the current schedule. Current schedule is much detailed and during the course of time I introduced many activities which were not known before but required to execute. Due to this reason I can not simply compare two schedules. Please help me to evaluate longest path of the completed (as built) schedule. My schedule is in P6 and I have used global change to de-progress it without scheduling it. But all bars are green in result and no critical or longest path is visible.
Please help.
Sri
Replies