HI,
I am a relative novice to planning and construction. At the moment I am carrying out a project planning programme for the construction of a school, using Primavera. Contract duration 18 months at a cost of £8million. I have assumed a plan size area of 3000m/squared.
I would appreciate if anybody could give some advice on the basic activities, their order and the RELATIVE DURATION it takes for each.
The programme has to comprise of at least 60 activites. Is it easier to just group all one type activity together ie. plasterboard and assign it the total cost for the whole project in Primevera.
Below is the outline of my schedule so far but I am not really happy with it as I don't know what half the activities really are!
Any advice on where to look for examples or advice on my order of schedule so far would be greatly appreciated!
Many thanks!
Stay Classy, Ross
TASK/ACTIVITY |
START PROJECT |
SITE PREPARATION |
Construct Perimeter Wall and Secure site |
Site Excavation |
Set out and level site |
Enabling works (Portakabin erection etc.) |
Mains Connection for Tools |
FOUNDATION/SUBSTRUCTURE |
Hire Scafolding |
Erect Scafolding |
Excavate and lay all underground services |
Footings |
Dig Footing and install reinforcingg |
Pour Footings |
Pin Footings |
Stock Block, Motor, Sand |
Build Block Foundations |
Erect ground beams |
Ensure ground drainage system |
Excavate for pipeworks |
Buy pipeworks and steelworks |
Install Pipeworks |
SUPERSTRUCTURE/STEEL CONCRETE WORKS |
Erecting structual steelwork |
Timber framing |
Metal profiled sheet decking |
CLADDING/COVERING |
Rainscreen cladding |
Sheet/Board cladding |
Concrete slab cladding |
Waterproofing |
WINDOWS/DOORS/STAIRS |
Windows |
Doors |
Stairs |
Glazing |
SURFACE FINISHES |
Plastering |
Tiling |
Coating paint to protect steelworks |
ROUGH CARPENTARY |
Frame walls |
Install wood/plythwood |
Roofing |
Install pipeworks |
Install gutters |
roof glazing |
roof slating |
Plumbing |
Procure pipeworks |
Install Pipeworks |
Water connection |
Install toilet/handbasins |
ELECTRICAL |
Lighting |
Alarm System |
Telephone/TV System |
Heating requirements |
AC installation |
INSULATION |
Air tight strips |
Double Glazing |
DRYWALL |
Stock drywall |
Hang drywall |
tape and finish drywall |
Sand drywall |
inset wall partitions |
PAINT AND VINYL |
Prime Coat |
Finishing Coat |
LANDSCAPING |
Carpark |
Pavements |
Patios |
Playground |
Gardens |
FINISHES |
Plumbing |
Electrical |
Paint touch up |
CLEAN UP |
Clean up and demobilize site |
Final Walkthrough |
PROJECT FINISH/COMPLETION |
TOTAL |
Replies