Construction activity scheduling for School Building

1 reply [Last post]
Ross Ritchie
User offline. Last seen 13 years 31 weeks ago. Offline
Joined: 29 Mar 2011
Posts: 2
Groups: None

HI,

I am a relative novice to planning and construction.  At the moment I am carrying out a project planning programme for the construction of a school, using Primavera. Contract duration 18 months at a cost of £8million.  I have assumed a plan size area of 3000m/squared.

I would appreciate if anybody could give some advice on the basic activities, their order and the RELATIVE DURATION it takes for each.

The programme has to comprise of at least 60 activites.  Is it easier to just group all one type activity together ie. plasterboard and assign it the total cost for the whole project in Primevera.

Below is the outline of my schedule so far but I am not really happy with it as I don't know what half the activities really are!

Any advice on where to look for examples or advice on my order of schedule so far would be greatly appreciated!

Many thanks!

 

Stay Classy, Ross

 

TASK/ACTIVITY
START PROJECT
SITE PREPARATION
Construct Perimeter Wall and Secure site
Site Excavation
Set out and level site
Enabling works (Portakabin erection etc.)
Mains Connection for Tools
FOUNDATION/SUBSTRUCTURE
Hire Scafolding
Erect Scafolding
Excavate and lay all underground services
Footings
Dig Footing and install reinforcingg
Pour Footings
Pin Footings
Stock Block, Motor, Sand
Build Block Foundations
Erect ground beams
Ensure ground drainage system
Excavate for pipeworks
Buy pipeworks and steelworks
Install Pipeworks
SUPERSTRUCTURE/STEEL  CONCRETE WORKS
Erecting structual steelwork
Timber framing
Metal  profiled sheet decking
CLADDING/COVERING
Rainscreen cladding
Sheet/Board cladding
Concrete slab cladding
Waterproofing
WINDOWS/DOORS/STAIRS
Windows
Doors
Stairs
Glazing
SURFACE FINISHES
Plastering
Tiling
Coating paint to protect steelworks
ROUGH CARPENTARY
Frame walls
Install wood/plythwood
Roofing
Install pipeworks
Install gutters
roof glazing
roof slating
Plumbing
Procure pipeworks
Install Pipeworks
Water connection
Install toilet/handbasins
ELECTRICAL
Lighting
Alarm System
Telephone/TV System
Heating requirements
AC installation
INSULATION
Air tight strips
Double Glazing
DRYWALL
Stock drywall
Hang drywall
tape and finish drywall
Sand drywall
inset wall partitions
PAINT AND VINYL
Prime Coat
Finishing Coat
LANDSCAPING
Carpark
Pavements
Patios
Playground
Gardens 
FINISHES
Plumbing 
Electrical
Paint touch up
CLEAN UP
Clean up and demobilize site
Final Walkthrough
PROJECT FINISH/COMPLETION
TOTAL 

Replies

farnas ap
User offline. Last seen 7 years 25 weeks ago. Offline
Joined: 5 Apr 2014
Posts: 7
Groups: None

I THINK IT MAY OUT DATE.

But someone can help this post...........

here r some activites.............

Activity NameOriginal Duration
City Center Office Building Addition681
  Design and Engineering107
    Design Building Addition55
    Start Office Building Addition Project0
    Review and Approve Designs22
    Assemble Technical Data for Heat Pump7
    Review Technical Data on Heat Pumps27
  Foundation146
    Begin Building Construction0
    Site Preparation43
    Excavation24
    Install Underground Water Lines12
    Install Underground Electric Conduit12
    Form/Pour Concrete Footings24
    Concrete Foundation Walls24
    Form and Pour Slab12
    Backfill and Compact Walls5
    Foundation Phase Complete0
  Structure151
    Erect Structural Frame48
    Begin Structural Phase0
    Floor Decking34
    Concrete First Floor36
    Erect Stairwell and Elevator Walls24
    Concrete Basement Slab24
    Concrete Second Floor36
    Structure Complete0
  Mechanical/Electrical Systems562
    Rough-In Phase Begins0
    Rough In Complete0
    Elevator218
      Install Elevator Rails and Equipment3
      Install Elevator Cab and Finishes5
    HVAC562
      Prepare and Solicit Bids for Heat Pump15
      Review Bids for Heat Pump10
      Award Contract for Heat Pump6
      Fabricate and Deliver Heat Pump and Controls422
      Install HVAC Ducts24
      Insulate Ducts5
      Set Heat Pump12
      Relocate HVAC Chiller7
      Startup and Test HVAC2
      Install AC Grills and Registers5
      Test and Balance HVAC Equipment2
    Plumbing and Electrical258
      Set Mechanical and Electrical Equipment36
      Rough-In Plumbing/Piping3
      Install Wiring and Cable36
      Connect Equipment1
  Exterior Finishes336
    Close-In Phase Begins0
    Building Enclosed0
    Brick312
      Assemble Brick Samples0
      Review and Approve Brick Samples30
      Prepare and Solicit Bids for Brick Exterior15
      Review Bids for Brick15
      Award Contract for Brick5
      Deliver Brick1
      Brick Exterior Walls17
    Roof24
      Insulation and Built-up Roofing24
    Doors and Windows7
      Install Door and Window Frames3
      Install Exterior Doors and Windows5
  Interior Finishes601
    Drywall in Offices36
    Touch-up and Clean-up2
    Finishes Complete0
    Punch List5
    Building Addition Complete0
    Plumbing and Lighting Fixtures44
      Install Lighting Fixtures7
      Install Plumbing Fixtures5
    Floor and Carpeting581
      Assemble and Submit Flooring Samples0
      Review and Approve Flooring28
      Prepare and Solicit Bids for Flooring24
      Review Bids for Flooring15
      Award Contract for Flooring5
      Fabricate and Deliver Flooring279
      Install Floor and Carpeting12
    Carpentry59
      Install Ceiling Grid36
      Finish Carpentry and Millwork12
    Paint12
      Paint Building Interior12
  
  
  
  
  

may be u need any assiatance u can catch up on me at my mail id