Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

how to generate S Curve in P6

1 reply [Last post]
Prasant Kumar Mah...
User offline. Last seen 13 years 46 weeks ago. Offline
Joined: 3 Apr 2007
Posts: 3

Hi all,

Normally we do our S curve in excel,but I wanted to know 'how the S curve is generated in P6?

Replies

Shah. HB
User offline. Last seen 1 year 3 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi Prasant

  1. you check through resource usage profile option icon placed below menu bar 
  2. Through values present in resource assignment option by manually coping and pasting in XL