Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Eanred Value rules for M&E procurement

3 replies [Last post]
Gary Whitehead
User offline. Last seen 5 years 25 weeks ago. Offline
Typically a project will earn the value of major M&E kit according to a series of milestones such as order placed, FAT, delivery & installation. The milestones used and % split of value across them is aligned with the T&Cs of the PO.

But I am curious to know what general rules or guidelines do fellow planners follow when developing inital baseline, before the T&Cs are known? And do these guidelines vary across regions and industries?

Replies

Shah. HB
User offline. Last seen 49 weeks 4 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi Gray

I have come across a case in which the specification states that delivery of materials Eg,-Generator ,at site cost 75% of Budgeted Value and remaining 25 % goes to the respective installation Activities
Shah. HB
User offline. Last seen 49 weeks 4 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi Gray

Are u looking for Earned Value procedure in MEP or WBS in developing the MEP Baseline schedule
Gary Whitehead
User offline. Last seen 5 years 25 weeks ago. Offline
I’m looking for how you apportion the budget cost & assocaited earned value of major M&E kit in your baseline programme

e.g. perhaps 10% of the value is earned when the order is placed, 50% throughout manufacturing period, 10% at FAT and 30% on delivery