Eanred Value rules for M&E procurement

S
Shah. HB 👤 Member for 17 years 8 months

Hi Gray



I have come across a case in which the specification states that delivery of materials Eg,-Generator ,at site cost 75% of Budgeted Value and remaining 25 % goes to the respective installation Activities

S
Shah. HB 👤 Member for 17 years 8 months

Hi Gray



Are u looking for Earned Value procedure in MEP or WBS in developing the MEP Baseline schedule

G
Gary Whitehead 👤 Member for 17 years 4 months

I’m looking for how you apportion the budget cost & assocaited earned value of major M&E kit in your baseline programme



e.g. perhaps 10% of the value is earned when the order is placed, 50% throughout manufacturing period, 10% at FAT and 30% on delivery

Featured Partner

Top Posters

PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts