PHYSICAL PROGRESS

1 reply [Last post]
Vishnu Kant Mishra
User offline. Last seen 13 years 39 weeks ago. Offline
Joined: 14 Feb 2009
Posts: 34
Groups: None
as per my client’s demand i was finding difficulty to show physical progress in p6.it is showing as per 2 activitywise but when i want 2 see d summary then it was not displaying as total in activity wbs summary. so how can i reflect it as %ge.

Replies

Rodel Marasigan
User offline. Last seen 4 days 9 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Vishnu,
All Activity Percent Type (Physical, Duration & Unit) are represented by Activity % complete and Performance % Complete. Use Performance % complete as it has summary but if your program is not cost loaded your summary band will be zero.