at the moment we are going through a retendering exercise for these works.
i am preparing an interface schedule to let the tenderers know locations of their works, when they can tentatively come in, when they need to finish to allow the other contractor to commence their work, etc....
hence i need to be reasonable and fair with the durations and estimations that i make as to when this particular tenderer can come in and do their work.
the easiest way to do this is to give them a start milestone as to when they will start and a finish milestone as to when they should finished.
the main problem by doing the above, is the tenderer will not be able to identify the various/numerous interfaces they will have with the other subcontract works.
hope the above helps in explaining why and what i am doing.
You say that there are a large number of store rooms in the catering facility and still the specialist contractor will not tell how long it will take fior them to install!
Are they not contractually obliged to reveal their programme.
If work has not yet started then make a condition in the tender and / or part of the prequalification document.
If they do not tell you how long it will take then they are off the bid list.
Please assist me - I do not understand the phrase "Pull-down of slab"
Pull-down of slab will take around 4-5 days after 28 day curing of the slab. make sure the required dehumidifiers are already working before you pull down the slab.
Just to give you an idea, to construct a cold slab with an area of 85x100, it would take around 5-6 weeks from slab preparation to pouring.
Installation of Freezer Panels, around 75LM per day is conservative.
Pull-down of slab will take around 4-5 days after 28 day curing of the slab. make sure the required dehumidifiers are already working before you pull down the slab.
You will also need underslab heating to stop frost driven ground heave but Sudharma says he knows all about the interfaces - he just wants to know how long it will take to put the store up.
A good starting point might be if we knew:
1. Is it inside another structure - if so is there access for trucks?
2. How big is it.
3. Is there only one of them.
You are right it will not take long to throw up the insulation panels once the structural frame and windposts are in place.
Its the cooling kit that will take time to install - is this fan driven or water chilled?
1. foundations will take time - the base of your cold storage room has some pipings for drainage.
2. piping works and the machine room
3. Insulated panels are easy to install (you might be surprised in 3 days your storage is closed)
4. if your storage has concrete flooring (then you need time to properly cure the concrete before you can apply the lining - lining takes time as well).
If they are your sub-contractor or prospective sub-contractor it is proper that they should tell you the durations of their work for incorporation in the main programme.
Since it is a specialist work, they are reluctant to divulge the information.
what i am trying to establish is the reasonable durations it would take to do the works, so that when i assess the program submission, i would be able to tell whether they r being resoanable or ridiculous with their durations.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Mike
at the moment we are going through a retendering exercise for these works.
i am preparing an interface schedule to let the tenderers know locations of their works, when they can tentatively come in, when they need to finish to allow the other contractor to commence their work, etc....
hence i need to be reasonable and fair with the durations and estimations that i make as to when this particular tenderer can come in and do their work.
the easiest way to do this is to give them a start milestone as to when they will start and a finish milestone as to when they should finished.
the main problem by doing the above, is the tenderer will not be able to identify the various/numerous interfaces they will have with the other subcontract works.
hope the above helps in explaining why and what i am doing.
thanks for the various feedbacks.
rgds
sudharma
Hi Sudharma
You say that there are a large number of store rooms in the catering facility and still the specialist contractor will not tell how long it will take fior them to install!
Are they not contractually obliged to reveal their programme.
If work has not yet started then make a condition in the tender and / or part of the prequalification document.
If they do not tell you how long it will take then they are off the bid list.
Best regards
Mike Testro
Hi Se
Please assist me - I do not understand the phrase "Pull-down of slab"
Pull-down of slab will take around 4-5 days after 28 day curing of the slab. make sure the required dehumidifiers are already working before you pull down the slab.
Can you explain further?
Best regards
Mike Testro
Shahul
Thanks for the advice
There are quite a number of cold rooms for this catering facility, the largest one the size is 33 meters in length while the width is about 11 meters.
At the moment the interfaces or sequence of works i had worked out is as follows:
1. Structural setdown
2. Refrigeration piping
3. Floor insulation installation
4. Cold rooms (walls & ceiling)
5. Backfilling concrete
6. Slotted drain positions
7. Internal screeding
8. Epoxy floor painting
9. 1st fix electricals
10. 1st fix fire fighting systems
11. 2nd fix electricals
12. 2nd fix fire fighting systems
13. Cooling coils unit installation
14. Condensation piping installation
15. Cold room door installation
16. Bumper installation inside & outside cold room (for protection of the cold room wall panels)
There are also interfaces with the other systems which are done by other contractors.
rgds
sudharma
Just to give you an idea, to construct a cold slab with an area of 85x100, it would take around 5-6 weeks from slab preparation to pouring.
Installation of Freezer Panels, around 75LM per day is conservative.
Pull-down of slab will take around 4-5 days after 28 day curing of the slab. make sure the required dehumidifiers are already working before you pull down the slab.
I hope this helps.
Hi to all
@Sudharma C
you could post the activity with quantities then duration could be determined through the discussion in this forum
Hi Anoon
You will also need underslab heating to stop frost driven ground heave but Sudharma says he knows all about the interfaces - he just wants to know how long it will take to put the store up.
A good starting point might be if we knew:
1. Is it inside another structure - if so is there access for trucks?
2. How big is it.
3. Is there only one of them.
You are right it will not take long to throw up the insulation panels once the structural frame and windposts are in place.
Its the cooling kit that will take time to install - is this fan driven or water chilled?
Best regards
Mike Testro
Sudharma,
heres some hint:
1. foundations will take time - the base of your cold storage room has some pipings for drainage.
2. piping works and the machine room
3. Insulated panels are easy to install (you might be surprised in 3 days your storage is closed)
4. if your storage has concrete flooring (then you need time to properly cure the concrete before you can apply the lining - lining takes time as well).
cheers!
Hi Sudharma
If they are your sub-contractor or prospective sub-contractor it is proper that they should tell you the durations of their work for incorporation in the main programme.
Insist that they give you the information.
Best regards
Mike Testro
thanks for the input.
Since it is a specialist work, they are reluctant to divulge the information.
what i am trying to establish is the reasonable durations it would take to do the works, so that when i assess the program submission, i would be able to tell whether they r being resoanable or ridiculous with their durations.
rgds
sudharma
Hi Sudharma
Ask your specialist supplier.
Best regards
Mike Testro