Producing a programme for multiple rooms - Intended stagger 4No. rooms at a time with a weeks stagger.
If the intended sequence has inevitable changed during the course of the progress update how would you "keep" the intended stagger (e.g. for resources) once the "stagger activities" - the activities common in all rooms on the critical path used to link one room to another) have been completed and the remaining activities "stack up".
To overcome this problem I have identified a number of "stagger activities" throughout the programmeto ensure that once 1 stagger activity has been completed the remaining activities do not completely stack up.
The activities after the completed “stagger activity” up to the next “stagger activity” will stack up but will show varied float to the next stagger activity.
After every reschedule the process of re-linking etc is a lengthy process, is there a way you can level / constraint resources so that the programmewill automatically ensure the 4No. rooms are achievable?
Many Thanks
Replies