Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 - Resource Loading (Budgeted Units)

5 replies [Last post]
Steve Ogrady
User offline. Last seen 11 years 44 weeks ago. Offline
Joined: 17 Dec 2008
Posts: 18
Groups: None
I would like to start applying budgeted units to activities within my schedule. Scenario:

My schedule is based on 6 day/week @10hrs/day. Some resources are utilized on applicable activities for 10hrs/day.

In the case above: How do I do I load resources to the activities while taking in to account Reg. and Overtime Rates? Reg. Rate= 8hrs/day, OT Rate=2hrs

Keep in mind that I will have to insert actual mhrs/cost against this activity in the future

Any help on the setup of this would be great!

Thanks

Replies

Khuong Do
User offline. Last seen 2 years 33 weeks ago. Offline
Joined: 21 Feb 2010
Posts: 118
Groups: None

Hi,

I wrote an article regarding How to assign resource / resource loading / make resource plan in Primavera P6.

If you're interested, kindly read it here https://doduykhuong.com/2017/03/07/how-to-assign-resource-resource-loading-make-resource-plan-in-primavera-p6/

Izam Zakaria
User offline. Last seen 7 years 50 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
yeah i guess so. The productivity will become worst since you spend more hours but less progress (people not like a robot to have consistent energy).what kind of tools are you working for now?P3 or P6 .... maybe I can show u something useful about resource levelling.I’ve been done this when I was at offshore last time and it works perfectly.... pls get my email...aizam.zakaria@sbmoffshore.com
Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Steve
10h/day is quite normal for construction site, 14 hours maybe possible for a short period, e.g. a turnaround. Longer periods: no, in my opinion - human beings, no robots.
I agree to your idea to collect manhours on wbs-summaries (or levels of effort). This will make live easier for reporting progress and reports from construction site will be more reliable. You’ll just add the columns Actual Labour Units and Actual Overtime Labour Units to your resource assignments. For the actual costs P6 will calculate normal hours with the normal rate assigned to this activity and equivalent for the overdue hours. So you’ll better do with the real rate and overdue factor plus additional costs (camp, tools, etc.). Accuracy will satisy project planning.
Planning: A blended rate would destroy your calculation of actual costs. For planning purpose maybe the normal rate for all planned hours plus an extra (expenses) will work. OR you’ll assign the resources a second time with different rates.
Alternatively: You’ll mix planning and accounting issues. All real cost you’ll (probably) find in project accounting.
My humble opinion
Dieter
Steve Ogrady
User offline. Last seen 11 years 44 weeks ago. Offline
Joined: 17 Dec 2008
Posts: 18
Groups: None
Project mandate is that all contractors will be required to work 10hrs/day. Therefore I will have to show 8hrs/day reg. time and 2 hrs/day OT. I thought about a blended rate (Rate per Trade = Total Trade/(Reg+OT) - not sure if that would work when inputing actuals?

To anwser your question: Yes there will be times when these contractors will work 14,15,16 hrs days (all at the OT rate.

Question about tracking activities within the schedule:

There are many line items (activities) within the schedule. I am currently resource loading every activity for the purpose of creating a baseline schedule. These activities will roll up (hrs and cost for resources) to the WBS Summary. Is it possible to track (feed) actuals into the WBS Summary rather than into each activity, which would be laborus for both myself and the contractor. Your experienced thoughts/comments would be much appreciated.

Thanks.
Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Steve
You plan with 10 hours a day; do you really intend to plan with overtime on top? While a project is in progress overdue hours happen - again on top? For my experience, projects with planned overdue hours are about to fail.
In P6 you can’t plan with overdue hours. But you can enter actual overdue hours. Costs for those units will be calculated by price*hours*ot_factor. You can enter them either using time-sheets or directly for the resource assignments.
Regards
Dieter