yeah i guess so. The productivity will become worst since you spend more hours but less progress (people not like a robot to have consistent energy).what kind of tools are you working for now?P3 or P6 .... maybe I can show u something useful about resource levelling.Ive been done this when I was at offshore last time and it works perfectly.... pls get my [email protected]
10h/day is quite normal for construction site, 14 hours maybe possible for a short period, e.g. a turnaround. Longer periods: no, in my opinion - human beings, no robots.
I agree to your idea to collect manhours on wbs-summaries (or levels of effort). This will make live easier for reporting progress and reports from construction site will be more reliable. You’ll just add the columns Actual Labour Units and Actual Overtime Labour Units to your resource assignments. For the actual costs P6 will calculate normal hours with the normal rate assigned to this activity and equivalent for the overdue hours. So you’ll better do with the real rate and overdue factor plus additional costs (camp, tools, etc.). Accuracy will satisy project planning.
Planning: A blended rate would destroy your calculation of actual costs. For planning purpose maybe the normal rate for all planned hours plus an extra (expenses) will work. OR youll assign the resources a second time with different rates.
Alternatively: You’ll mix planning and accounting issues. All real cost you’ll (probably) find in project accounting.
Project mandate is that all contractors will be required to work 10hrs/day. Therefore I will have to show 8hrs/day reg. time and 2 hrs/day OT. I thought about a blended rate (Rate per Trade = Total Trade/(Reg+OT) - not sure if that would work when inputing actuals?
To anwser your question: Yes there will be times when these contractors will work 14,15,16 hrs days (all at the OT rate.
Question about tracking activities within the schedule:
There are many line items (activities) within the schedule. I am currently resource loading every activity for the purpose of creating a baseline schedule. These activities will roll up (hrs and cost for resources) to the WBS Summary. Is it possible to track (feed) actuals into the WBS Summary rather than into each activity, which would be laborus for both myself and the contractor. Your experienced thoughts/comments would be much appreciated.
You plan with 10 hours a day; do you really intend to plan with overtime on top? While a project is in progress overdue hours happen - again on top? For my experience, projects with planned overdue hours are about to fail.
In P6 you cant plan with overdue hours. But you can enter actual overdue hours. Costs for those units will be calculated by price*hours*ot_factor. You can enter them either using time-sheets or directly for the resource assignments.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi,
I wrote an article regarding How to assign resource / resource loading / make resource plan in Primavera P6.
If you're interested, kindly read it here https://doduykhuong.com/2017/03/07/how-to-assign-resource-resource-loading-make-resource-plan-in-primavera-p6/
yeah i guess so. The productivity will become worst since you spend more hours but less progress (people not like a robot to have consistent energy).what kind of tools are you working for now?P3 or P6 .... maybe I can show u something useful about resource levelling.Ive been done this when I was at offshore last time and it works perfectly.... pls get my [email protected]
Steve
10h/day is quite normal for construction site, 14 hours maybe possible for a short period, e.g. a turnaround. Longer periods: no, in my opinion - human beings, no robots.
I agree to your idea to collect manhours on wbs-summaries (or levels of effort). This will make live easier for reporting progress and reports from construction site will be more reliable. You’ll just add the columns Actual Labour Units and Actual Overtime Labour Units to your resource assignments. For the actual costs P6 will calculate normal hours with the normal rate assigned to this activity and equivalent for the overdue hours. So you’ll better do with the real rate and overdue factor plus additional costs (camp, tools, etc.). Accuracy will satisy project planning.
Planning: A blended rate would destroy your calculation of actual costs. For planning purpose maybe the normal rate for all planned hours plus an extra (expenses) will work. OR youll assign the resources a second time with different rates.
Alternatively: You’ll mix planning and accounting issues. All real cost you’ll (probably) find in project accounting.
My humble opinion
Dieter
Project mandate is that all contractors will be required to work 10hrs/day. Therefore I will have to show 8hrs/day reg. time and 2 hrs/day OT. I thought about a blended rate (Rate per Trade = Total Trade/(Reg+OT) - not sure if that would work when inputing actuals?
To anwser your question: Yes there will be times when these contractors will work 14,15,16 hrs days (all at the OT rate.
Question about tracking activities within the schedule:
There are many line items (activities) within the schedule. I am currently resource loading every activity for the purpose of creating a baseline schedule. These activities will roll up (hrs and cost for resources) to the WBS Summary. Is it possible to track (feed) actuals into the WBS Summary rather than into each activity, which would be laborus for both myself and the contractor. Your experienced thoughts/comments would be much appreciated.
Thanks.
Steve
You plan with 10 hours a day; do you really intend to plan with overtime on top? While a project is in progress overdue hours happen - again on top? For my experience, projects with planned overdue hours are about to fail.
In P6 you cant plan with overdue hours. But you can enter actual overdue hours. Costs for those units will be calculated by price*hours*ot_factor. You can enter them either using time-sheets or directly for the resource assignments.
Regards
Dieter