editing actual date

2 replies [Last post]
Nar Thap
User offline. Last seen 16 years 36 weeks ago. Offline
Joined: 12 Sep 2007
Posts: 73
experienced a typical, never happened problem in suretrak. alredy completed activity with actuals on both ES & EF. Now it is realised that the activity has not completed yet so I put 5d Rem Duration and wanted to change EF accordingly. Surprisingly, the EF everytime stayed at DD and the bar is not extending beyond DD. All auto cost rules are ticked. Anybody can give me the solution?

Replies

Nar Thap
User offline. Last seen 16 years 36 weeks ago. Offline
Joined: 12 Sep 2007
Posts: 73
Sikandar,
did not worked yet. found where was the problem and able to solve it. The reason behind was the already driven resorce.Thanks for your suggestion anyway.
Shahzad Sikandar
User offline. Last seen 6 years 30 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
what was the original duration ?
check actual duration / units are zero

and also percnet complete should be zero.

then put remaining days,

try this

might work

cheers