Information Schedule

1 reply [Last post]
Ahmed Saudagar
User offline. Last seen 2 weeks 10 hours ago. Offline
Joined: 30 Jan 2006
Posts: 10
Groups: GPC Qatar

Request info on information schedule.

If I understsand correctly, the Information Schedule has a similar function as to the Long Lead Schedule except that this deals with items that do not form a part of the events in the plan.

Request help by means of a typical format and sample if available.

Replies

Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
please understand my understanding as it is not functioning properly! but if i understand you correctly, there’s no such thing as information schedule not forming part of the events in your plan! because it will eventually and inevitably be part of it!

I guess you’re referring to MEP long lead items, i.e. machineries, which you, as MEP contractor only can provide!