Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

MEP

2 replies [Last post]
Pacifico Pallasigui
User offline. Last seen 12 years 22 weeks ago. Offline
Joined: 24 Jan 2004
Posts: 62
Groups: None
I have here activities for Mechanical ,Electrical & Plumbing installation for our project in russia a multi functional building project.

MECHANICAL & PLUMBING INSTALLATIONS

1. Heating Station
2. Smoke Protection & Ventilation System
3. Heating & Cooling System
4. Heating System Floor Convector
5. Mechanical Vertical shafts
6. PLUMBING - DOMESTIC, COLD & HOT CIRCULATION SYSTEM
7. SPRINKLER AND HOSE REEL SYSTEM
8. DOMESTIC & STORM WATER DRAINAGE SYSTEM
9. BMS SYSTEM
10. COOLING SYSTEM (CHILLERS & DRY-COOLERS ON THE ROOF)

ELECTRICAL INSTALLATIONS

1. ELECTRICAL SUBSTATION
2. EARTHING & LIGHTNING PROTECTION SYSTEMS
3. POWER DISTRIBUTION SYSTEM
4. ELECTRIC LIGHTING SYSTEM
5. RADIO SYSTEM
6. TV SYSTEM
7. CCTV (CLOSED CIRCUIT TELEVISION) SYSTEM
8. FIRE ALARM & PUBLIC ADDRESS SYSTEM
9. CLOCK SYSTEM
10. TELECOMMUNICATION SYSTEM
11. SECURITY SYSTEM


My Questions:

a. What systems or activities are included in TESTING & COMMISSIONING?
b. Around How many months is Testing & Commisioning (Duration)?
c. When is the proper timing or relationship to start Testing & Commisioning?
d. What is the relation of this list activities example: power distribution needed to start some systems.

Can anybody help me because im a civil engineer and have no experience in MEP.

Thanks

Pacifico

Replies

Pacifico Pallasigui
User offline. Last seen 12 years 22 weeks ago. Offline
Joined: 24 Jan 2004
Posts: 62
Groups: None
Thanks for all the help & tips bro

The project is a two building one is 7 storey bldg and adjacent to that is a 9-storey building and this two buildings is divided by an atrium.

Thanks
pacifico
Pranab Kumar Deb
User offline. Last seen 3 years 22 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
dear Sir,

a.TESTING & COMMISSIONING is rquired for all the system listed above i.e u have to connect all the systems above with an activity name "TESTING & COMMISSIONING" at the end.
b. Depends on the built up area of the building , nos of flooors how much resources u have and all .
c. It can start after the set up for the system has been completed personally i prefer this activity at the end of completion of the set up.
d. Power distribution is needed for all the listed systems.
for a copy of my project u can mail me deb.icd@tajnet.com
i may be late to reply as will move out on vacation
regards
deb