Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Production rates - timber doors and windows

4 replies [Last post]
John Lowry
User offline. Last seen 1 year 30 weeks ago. Offline
Joined: 9 May 2005
Posts: 4
Groups: None
Does anyone have production rates for timber framed and glazed doors and windows?

What are the likely procurement and lead-in times for materials supply, planning, workshop drawings and manufacture?

Replies

Christian Adrian ...
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 3 Jun 2003
Posts: 193
Groups: None
Hello Chaps

Perhaps there’s also some of you guys who would happen to know about fiber optic installation (production rate)too..
There’s none in the PP Prod. rates.

Thanks in advance...

Christian
John Lowry
User offline. Last seen 1 year 30 weeks ago. Offline
Joined: 9 May 2005
Posts: 4
Groups: None
Appreciate your comments Simon, particularly in relation to import times. The windows are Sirian Cedar (Malaysian). It is a small multi-residential project. Modern windows, large folding doors. Excluding timber procurement, I have allowed (in working days):
Mobilisation / read dwgs / prepare procurement schedules (once only) 5 days
For each group of 10:-
Site measure 2
Shop drawings 2
Approval 5
Set-up 2
Manufacture (incl glass) 14

Maybe I’m a bit light-on in some areas.
Hardware generally has a delivery time of 2 - 4 weeks in Aus.
Simon Mawdsley
User offline. Last seen 10 years 34 weeks ago. Offline
Joined: 22 Mar 2004
Posts: 11
Groups: None
John

This could take some time to answer as you may need to consider the timber delivery and kiln drying. What type of window will it be, Victorian or modern? What about the ironmongery and glazing.

I’ve just been through the mill (Joke) with 1500 Victorian style windows and doors of different shapes and sizes. It goes without saying that the choice of manufaturer makes a big differance to.

As a guide you could use
1) 6 weeks for import of timber (Including infestation check at customs.
2) 2 weeks to twice kiln dry
3) 1 day to rough cut
4) 1 days to mark -up
5) 3 days for routing
6) 2 days to construct (Incl Ironmongery
7) 4 days for painting

With regard to Shop drawings, if you are in a themed area that requires coordination with facades or other windows you should allow 2.5 days per drawing.
Sukumaran Subaram...
User offline. Last seen 9 years 18 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Check at Production Rate section. You can get a rates for most of the works.