Primavera P6 activity Bar

1 reply [Last post]
andrew francis
User offline. Last seen 11 weeks 2 days ago. Offline
Joined: 29 Aug 2013
Posts: 20
Groups: None

Dear sirs, I have recently moved from MSP back to Primavera P6.

I am trying to prevent the activity bar from reducing in size when using duration % i.e if the bar covers a 1 month duration with  known start and finish date and i apply  20% progress, the bar reduces in size by 20%. and if i apply 100% it ieffectively dissappears I have worked out that if i use fixed work the durtion remains the same size but if I apply some progress the work units do not reduce.

I dont recall having this issue in MSP?- What am i doing wrong or using incorrectly - i dont have anyone to ask ?

 

Andy 

Replies

david kelly
User offline. Last seen 4 hours 42 min ago. Offline
Joined: 12 Feb 2016
Posts: 36
Groups: None
What you are describing is what the bar dialogue call the ‘Remaining’ bar. There is no ‘Activity’ bar If you want to draw a bar from the Early start to Early finish – unaltered by progress the timescale you want in the second column of the barchart dialogue in ‘Plan Bar’ I recommend a wee P6 dates refresher. Google: Ron Winter Primavera Dates