Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavera P6 activity Bar

1 reply [Last post]
andrew francis
User offline. Last seen 2 weeks 15 hours ago. Offline
Joined: 29 Aug 2013
Posts: 18
Groups: None

Dear sirs, I have recently moved from MSP back to Primavera P6.

I am trying to prevent the activity bar from reducing in size when using duration % i.e if the bar covers a 1 month duration with  known start and finish date and i apply  20% progress, the bar reduces in size by 20%. and if i apply 100% it ieffectively dissappears I have worked out that if i use fixed work the durtion remains the same size but if I apply some progress the work units do not reduce.

I dont recall having this issue in MSP?- What am i doing wrong or using incorrectly - i dont have anyone to ask ?

 

Andy 

Replies

david kelly
User offline. Last seen 5 hours 36 min ago. Offline
Joined: 12 Feb 2016
Posts: 33
Groups: None
What you are describing is what the bar dialogue call the ‘Remaining’ bar. There is no ‘Activity’ bar If you want to draw a bar from the Early start to Early finish – unaltered by progress the timescale you want in the second column of the barchart dialogue in ‘Plan Bar’ I recommend a wee P6 dates refresher. Google: Ron Winter Primavera Dates