Dear sirs, I have recently moved from MSP back to Primavera P6.
I am trying to prevent the activity bar from reducing in size when using duration % i.e if the bar covers a 1 month duration with known start and finish date and i apply 20% progress, the bar reduces in size by 20%. and if i apply 100% it ieffectively dissappears I have worked out that if i use fixed work the durtion remains the same size but if I apply some progress the work units do not reduce.
I dont recall having this issue in MSP?- What am i doing wrong or using incorrectly - i dont have anyone to ask ?
Andy