Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Broken Bars in Bar Chart

2 replies [Last post]
AB Timo
User offline. Last seen 9 years 36 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

Hello All,

I have Prepared a schedule in P6 and after making initial schedule and Assigning cost to all activities (No Resource Loading Required for the project,only activity cost from BOQ),I saved the Schedule as Primry Baseline.Now When I update the Schedule the Bars before and after the Data date Line are broken.

This Problem is not occuring in Duration % Complete type.Can anyone tell me the reason?

Replies

AB Timo
User offline. Last seen 9 years 36 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

but in duration % complete it is not the case.only in case of physical % complete.

Jash Sales
User offline. Last seen 12 years 43 weeks ago. Offline
Joined: 8 Dec 2009
Posts: 27
Groups: None

One reason of activity bar was broken is due to out of sequence realationship with its predecessor. Eventhough your activity is in progress if its driving predecessor is not yet completed or meet their relationship, still the predecessor will push your current bar and it will only start again once your predecessor is completed; thus, made the bar broken.