Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Is there any Relationship b/w Performance% complete value & Total float value.....???

5 replies [Last post]
abubakar munir
User offline. Last seen 6 years 16 weeks ago. Offline

Hi Seniors,

I want to know is there any relation b/w performance% complete value & total float value. In my case, my schedule % complete value is 15.5 & performance % complete value is 11.
against these percentages my plan showing the delay of -14 days. I want to know why is much difference btw my schedule & performance percentage where my delay is only for -14 days.

please help me out with finest one.


 

Replies

abubakar munir
User offline. Last seen 6 years 16 weeks ago. Offline

Thanxs zahid...
 

zahid shaikh
User offline. Last seen 5 years 35 weeks ago. Offline
Joined: 24 Aug 2016
Posts: 35

1) Schedule % complete is calculated in P6 wrt to Baseline Planned dates and Data Date.

Eg: Activity start and finish are 22-Dec-17 to 2-Jan18 i.e. duration is 12 days. When data date is 25-Dec-17, (22-Dec-17)-(25-Dec-17)=4days. Schedule % will be 4days/12 days = 27%. For data Date 29-Dec-17. Schedule % will be 64%.

 

2) For Performance %; It is calculated wrt to Duration % complete/Units % complete/Physical % complete, depending on how the progress is being recorded. I.e Performance % complete is = Duration % complete (assuming that the project is resource loaded)

abubakar munir
User offline. Last seen 6 years 16 weeks ago. Offline

Thanks for your response.
I did not get it what are you trying to ask me but according to my understanding, i am measuring the performance w.r.t time.

 

Waiting for your reply.

abubakar munir
User offline. Last seen 6 years 16 weeks ago. Offline

Thanks for your response.
I did not get it what are you trying to ask me but according to my understanding, i am measuring the performance w.r.t time.

 

Waiting for your reply.

Zoltan Palffy
User offline. Last seen 4 days 58 min ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

how are you measuring the performance ?