Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Re: HELP ON GLOBAL CHANGE

1 reply [Last post]
Tom Gouldburn
User offline. Last seen 11 years 32 weeks ago. Offline
Joined: 20 Aug 2012
Posts: 4
Groups: None

Hi Guys,

Hope all is well.

I'm new to p6 and have 3000 acitivites with incorect costing applied to activities

Would anyone be able to assist on helping me do a global change for removing budgeted cost/Actual cost ?

Thanks

Tom Gouldburn

Replies

Mike Testro
User offline. Last seen 33 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Tom

Can you not just delete the cost heads to clear them out and then add new ones.

That is what I would do in Asta Powerproject.

Best regards

Mike Testro