Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Is there a technical name for delay caused by not being able to work as scheduled? for example if something is FS instead of SS?

No replies
John Reeves
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Is there a technical name for delay caused by not being able to work as scheduled? for example if something is FS instead of SS? (for example thought could start steel same time as concrete but had to wait until done.)  "Out of Sequence Delay" or "Logic Error Delay" or "Planning Delay"?

Alex Lyaschenko
User offline. Last seen 6 weeks 1 day ago. Offline
Joined: 15 Aug 2011
Posts: 59
Groups: None

If a schedule has SS instead of FS (or any other combination) it is just a schedule quality issue that only could be solved by maturing schedule development process. 

Alex Lyaschenko
User offline. Last seen 6 weeks 1 day ago. Offline
Joined: 15 Aug 2011
Posts: 59
Groups: None

If a schedule has SS instead of FS (or any other combination) it is just a schedule quality issue that only could be solved by maturing schedule development process. 

Zoltan Palffy
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

any one of those is sufficent